Project timelines


Design work on the first stage of the Sydney Metro network is underway and construction will begin in 2010 to enable the metro to be opened to the public in 2015.

As a result of a joint State-Federal Government feasibility study, the preferred alignment and station locations for Stage 2 of the network, from Central to Westmead, have now been identified. Subject to future funding decisions, construction of this second stage could commence as early as 2011.

Timeline for Stage 1 (Rozelle - Central)

Quarter 1, 2009

Project Planning Application submitted support by Preliminary Environmental Assessment.

Quarter 2, 2009

Expression of interest for delivery contracts

Quarter 3 - Quarter 4, 2009

Preparation and public exhibition of Environmental Assessment

Quarter 4, 2009

Issue tenders for delivery contracts

Quarter 4, 2009

Project planning approval determination

Quarter 2 - Quarter 3, 2010

Award delivery contracts

Quarter 4, 2010 - Quarter 4 – 2014

Design and construct

Quarter 1, 2015 - Quarter 3 – 2015

Commissioning

Quarter 4, 2015

Operation

Back to top ^

Timeline for Stage 2 (Central - Westmead)

Quarter 3, 2009 

Project Planning Application submitted supported by Preliminary Environmental Assessment.

Quarter 3 - Quarter 4, 2009

Preparation of detailed Environmental Assessment

Quarter 1, 2010

Public exhibition of detailed Environmental Assessment

Quarter 3, 2010

Project planning approval determination