Stage 1 of 4
Project timelines
Design work on the first stage of the Sydney Metro network is underway and construction will begin in 2010 to enable the metro to be opened to the public in 2015.
As a result of a joint State-Federal Government feasibility study, the preferred alignment and station locations for Stage 2 of the network, from Central to Westmead, have now been identified. Subject to future funding decisions, construction of this second stage could commence as early as 2011.
Timeline for Stage 1 (Rozelle - Central)
Quarter 1, 2009
Project Planning Application submitted support by Preliminary Environmental Assessment.
Quarter 2, 2009
Expression of interest for delivery contracts
Quarter 3 - Quarter 4, 2009
Preparation and public exhibition of Environmental Assessment
Quarter 4, 2009
Issue tenders for delivery contracts
Quarter 4, 2009
Project planning approval determination
Quarter 2 - Quarter 3, 2010
Award delivery contracts
Quarter 4, 2010 - Quarter 4 – 2014
Design and construct
Quarter 1, 2015 - Quarter 3 – 2015
Commissioning
Quarter 4, 2015
Operation
Timeline for Stage 2 (Central - Westmead)
Quarter 3, 2009
Project Planning Application submitted supported by Preliminary Environmental Assessment.
Quarter 3 - Quarter 4, 2009
Preparation of detailed Environmental Assessment
Quarter 1, 2010
Public exhibition of detailed Environmental Assessment
Quarter 3, 2010
Project planning approval determination